renovation ruminations: part 8

After ten years lamenting the eyesore across the garden, the time had come to do something about it. It was so horrible, this is the only photo I could find.

A few bits of timber and tin had been thrown together to resemble sheds by the previous owners, handy storage but not pretty.

Demolition began in November 2018, a very satisfying exercise.

The initial plan to ‘use & re-use’ as much as possible with timber framed windows and doors from the salvage yard. I set to with a scraper, sander and heat gun, hoping to have them prepared before the builders needed them.

The new slab was poured in February (Poppy made her mark) as well as a smaller
3m x 3m and we possum-proofed them for a few days.

When we demolished the 6m x 3m tin shed we resurrected the best panels and turned it into a 3m x 3m shed, hence the smaller slab.

We finally pinned down the builder to do the frame in April, a hasty job that was left largely unfinished.

We completed the structural work with advice from a building surveyor and got on with the cedar cladding in the hope of being weatherproof before winter. The builders had put the colorbond on the roof but hadn’t finished the edges so we temporarily fixed some old flashings until we could find a roofer willing to finish the job. We had since realised the windows were a step too far, it would take far too long to restore them and the end result wouldn’t be as we pictured. We ordered new windows to match those on the house, another six week wait and we halted cladding until they arrived.

There was plenty more to keep us occupied. We finished wrapping the carport area and, with a few acrobatics involved, applied the colorbond to the outside.

A bit more cladding,

fitting the back door

and the new windows arrived two weeks early. We replaced the old ones and finished the cladding

but the season had changed and it was too cold to apply protection until summer.

Many years ago, Michael found an old door at the salvage yard that was too nice to leave there. It has rested in the garage for eight years and now has pride of place as the front door. With the warmer weather, I could finally attempt to restore it to its former glory.

More delays ensued waiting for the electrician and we were now into May 2020. Once his cabling was in, we fitted the insulation batts

and the plasterers were able to work their magic.

We had decided on epoxy resin with vinyl flakes for the floor and the next few weeks were a juggling act between the plumbers and the flooring contractor. With the heat pump installed we could paint through the cold months and apply architraves and skirtings.

A kitchenette is next and some comfy couches and we have a lovely music studio to relax in as well as a more pleasing vision across the garden.

renovation ruminations: part 6

Our latest renovation project has been a few years in the making. When we moved in, the back verandah was partly enclosed and there were café blinds further along (the first storm took care of those). Apart from being immensely unattractive, condensation would drip from the ridges of the corrugated ceiling, creating puddles on the floor.

1.before

We solved that problem with a new ceiling in 2011, adding skylights to allow light into the house.

2.new ceiling Dec 2011

We had often talked about how nice it would be to enclose the room but other things got in the way. Forward to spring 2016 when a pair of welcome swallows moved in. Each time they started to build a new nest, we would remove it. They were so persistent, we attached plastic to the cedar cladding and cardboard ‘lids’ to the coach lights. They finally got the message – and so did we. In March this year, we started by removing the existing window and sliding door in readiness for a concrete slab.

A few days later, the builders started on the formwork, under the guidance of Poppy.

The driver manoeuvred the truck past the pond

8.concrete truck

and the lads got to work.

A few turns with the whirly-gig

14.whirly-gig

and next morning we had the beginnings of our new room.

15.slab

The old sliding door was repositioned at the entrance and a smaller window installed next to it.

16.new window, old sliding door

Three large stacker doors and a slider at the other end followed. The small stacker windows at the far end will sit above the bar and will open into the BBQ area. Poppy has a new doggy door which she thinks is great fun.

We left a channel open along the old exterior wall to allow access to pipes. The plan was to build timber frames so we could cover them with the flooring but remove if we have plumbing problems. Michael’s mammoth trench-digging effort unearthed the pipes but they weren’t where we thought, they were more central in the room.

19.trench for plumber

The old coach lights were removed and down lights installed, with power points to follow. We sanded the existing window frames so they would match the new ones.

20.sanding

We carefully extricated the cladding from the old exterior wall

and after attaching the moisture proof membrane,

23.waterproofing

re-used it on the new exterior.

Insulation came next

27.insulation

and then the plumber removed the old exterior pipes, re-directed them outside and installed fixtures for a bar sink. Now that we didn’t need the channel to access the pipes, we had another concrete delivery to fill it in

and laid a slab for the BBQ and pizza oven at the same time.

30.BBQ slab

Plastering and painting made it all seem a reality.

31.almost there

We decided on a small wood heater for those cold winter evenings,

32.wood heater

and vinyl planks for the floor. The excitement of laying the first plank

33.first plank

had quelled somewhat after the second day.

34.halfway

With skirtings fitted and varnished, we are very happy with the result.

35.finished

Poppy has a new bed (she refused to smile for the camera) made from reclaimed timber.

36.Poppy's bed

We couldn’t make up our minds on furnishings so decided to refurbish the items we already had.

We bought an old pew for our dining area, it revived beautifully with some TLC.

45.pew

The dining table and coffee table – well, that’s another story. Now we just have to build the bar, a couple of cupboards, the decking, the BBQ………